A roofing project and a sign project can reach the same building through very different schedules. The roofing contractor may be preparing an area for repairs while the sign crew is planning removal, installation, or service above it. If those plans meet for the first time on the workday, the property manager has a coordination problem.
Bring the sign contractor into the conversation before roof work begins. The goal is to agree on access, responsibilities, and the sequence of work around the actual sign and roof conditions. That gives each contractor a clearer understanding of what must happen before the next crew can proceed.
At Addisigns, our installation planning starts with the site. Rooftop work makes that preparation especially important because the mounting area, roof surface, and equipment approach need to be considered together.
Identify exactly which work overlaps
Begin with a description of the roofing project and the sign work being considered. Is the roof being replaced beneath an existing sign? Does the sign need to come down temporarily? Will the roofing work affect access to wiring or supports? Are you installing a new sign while other building work is underway?
Share the available drawings and photographs with both contractors. Label the relevant roof area and sign location consistently. A building can have several roof levels, and “the west side” may mean different things to a roofing supervisor and a sign installer approaching from the parking lot.
Ask each contractor to identify the points where its work depends on the other. Put unresolved questions on a shared list rather than filling the gaps with assumptions about who normally handles them.
Arrange the survey before setting a firm sequence
The existing sign, mounting arrangement, and electrical access need professional assessment before removal or reinstallation is priced as a straightforward task. Previous drawings are useful background, but they may not show later repairs or changes to the building.
Our site surveys record measurements, mounting conditions, electrical access, and site photographs. For rooftop coordination, provide the roofing contractor's proposed work area and any access restrictions at the same time. The sign team can then identify questions that require discussion with the building owner or another qualified professional.
Do not treat a survey as permission to alter the roof or structural supports. Its purpose is to establish the information needed for the project. Any additional design, assessment, or approvals should be identified in the agreed scope before the work proceeds.

Agree on the approach to the roof
Discuss how people, tools, and sign components will reach the work area. Building access and equipment access are related, but they are not interchangeable. A route suitable for a maintenance worker may not accommodate a sign component, and a convenient parking space may not be an acceptable equipment setup location.
Give the sign team details about gates, locked doors, loading areas, occupied entrances, and scheduled deliveries. Let the contractors establish their access and work-zone requirements. The property manager's role is to supply accurate site information and coordinate availability, not to prescribe equipment placement.
Addisigns operates its own installation fleet, including crane and bucket trucks. Equipment selection still depends on the site and the task. Agree on the planned approach after assessment rather than assuming a previous visit establishes the method for a different job.
Resolve roof protection and restoration responsibilities
Ask the roofing contractor to explain the restrictions that apply to the new or existing roof assembly. Those may include how access should be managed, which areas must remain clear, and who may address roof details around sign-related work. Share those instructions with the sign contractor before scheduling.
Have the contractors identify who will handle any affected roof details and how completed work will be reviewed. If a roof warranty is involved, obtain the applicable requirements from the party responsible for that warranty. Do not assume that either contractor can speak for another company's coverage.
Record the agreed boundaries in the work orders. A short, specific description of each contractor's responsibility is more useful than a general statement that the roof will be “taken care of.” If the proposed scopes leave a gap, resolve it before authorizing the sequence.

Coordinate power and temporary sign removal
If the sign must be disconnected or removed, establish who is authorized to arrange that work and where the components will go. The plan should identify the electrical work, the removal operation, any storage needs, and the conditions for returning the sign to service.
Addisigns' installation service uses licensed electricians for electrical connections. Coordinate those tasks through the project team rather than asking building staff to disconnect unfamiliar sign equipment. The roofing and sign schedules should allow the appropriate professionals to complete their work in the agreed order.
For a sign being reused, request a condition record before removal. Photographs and component descriptions help everyone understand what was present at the start. Ask how damage or deterioration discovered during removal will be documented and how any additional repair recommendation will reach the owner for approval.
Use a sequence with clear handoff points
Build the schedule around readiness, not just calendar dates. Identify when the sign area becomes accessible, when the roofing contractor expects its relevant work to be complete, and what confirmation the sign contractor needs before returning. Include the owner or property manager as the decision contact.
Allow for discoveries that cannot be confirmed until work begins. If conditions differ from the original scope, the team needs a way to pause the affected task, document the issue, and agree on the next step. Avoid promising tenants a final completion date before those dependencies are understood.
After the work, arrange a handoff covering the sign's operation and the roofing contractor's review of its own completed scope. Keep the final records together so future service contractors can understand what changed and whom to contact with questions.
Start with a coordinated site conversation
Rooftop sign work benefits from a property manager who brings the right people together early. Send us the site address, the roofing contact, available drawings, and a description of the planned work. Tell us whether the sign will remain, be removed temporarily, or be replaced.
Our Tucson-based team provides sign installation across Southern Arizona and the Phoenix area. Call 520-748-1540 or request a project quote. We can help identify the survey and coordination work needed before the crews arrive.